Sydney Metro Northwest – Cheltenham Services Facility – May 2018

You may have seen that Construction has begun on the new Cheltenham Community Facility at Cheltenham Oval.

Construction timeline

1.Removal of vegetation: early April – to be complete by the end of April 2018

2.Excavation works: to be complete by end of April 2018

3.Building of structures: to be complete by the end of July 2018

4.Building finishing works: to be complete by the end of November 2018

5.Commissioning of facilities: to be complete by December 2018

.

You can read all about in on the Sydney Metro website at  https://www.sydneymetro.info/station/cheltenham-services-facility

We are looking forward to having the oval and improved facilities for the 2019 season.