You may have seen that Construction has begun on the new Cheltenham Community Facility at Cheltenham Oval.
Construction timeline
1.Removal of vegetation: early April – to be complete by the end of April 2018
2.Excavation works: to be complete by end of April 2018
3.Building of structures: to be complete by the end of July 2018
4.Building finishing works: to be complete by the end of November 2018
5.Commissioning of facilities: to be complete by December 2018
You can read all about in on the Sydney Metro website at https://www.sydneymetro.info/station/cheltenham-services-facility
We are looking forward to having the oval and improved facilities for the 2019 season.